Directions:

Obtain project details by selecting the desired project on the map, or review a list of unmapped projects from the link above.


Lee's Summit, MO

Water Main - Harris Road (Herring to Haines)

Last Updated

03/01/2018

Project Manager(s):

John Persing
816-969-1800

Estimated Construction Dates:

Feb 01, 2019 - Mar 01, 2019

Project Status

In Design

Project Description:

Rehabilitation and upsizing of 3 inch water main to a 12 inch water main along Harris Road from Herring Road to Haines Road.

Project Rationale:

Continued efforts to maintain and strengthen our water distribution system.

Current Project Status:

Project is in early design phase.


Water Main - Lakewood Way - Ridgewood to Bowlin Rd

Last Updated

03/16/2018

Project Manager(s):

Karen Quackenbush
816-969-1800

Estimated Construction Dates:

Apr 01, 2019 - Mar 31, 2018

Project Status

In Design

Projected Funding:

$400,000

Project Description:

Connect existing Waterlines at Ridgewood and Bowlin Road to create a looped system.

Project Rationale:

Continued efforts to maintain and strengthen our water distribution system.

Current Project Status:

Project is currently in design.